Update 7-2022

Overview
We are excited to share plans and updates with you for the Coosawattee portion of our ReConnect Fiber build.
* Currently engineering
* Build will be completed in 7 different phases
* Phases will be built in order, one at a time
* Each phase will have two parts: a construction period and then customer installations
* Build schedule is an estimate and is subject to change
* Schedule for other phases will be determined as progress is being made on current phase
At the appropriate time, property owners will be contacted, or directed to contact ETC, to get their orders lined up.
Key to Success!
We can do installations quicker with your help.Our goal is to maximize the number of fiber installations we can do per day.
Property owners who are flexible with their appointment time enable us to work more appointments in a day.
The more flexible owners can be, the quicker we can move through the phase.
CRRA Master Phase Map